Agenda for the first community design workshop on February 11th, 2016

P&Z Preliminary Design Review Hearing, 11/14/16 - design approved

The Argyros launch reception - February 20th, 2017

P&Z Design Review Hearing, 2/27/17 - design approved

Council Meeting, 4/17/17 - City Parking Ordinance Amendment approved

Council Meeting, 5/15/17 - Development Exceedance Agreement approved

All entitlements in hand - May 15th, 2017

Building Permits Issued - June 2017

Ground-breaking - July 7th, 2017

Start Demolition - July 2017

Start Excavation - August 2017

Start Foundations - October 2017

Out of the ground - January 2018

First steel erected - February 2018

Slides from update reception - February 22nd, 2018

 